The First Phase of
construction of the marina, which involves building
44 of the originally-planned 210 yacht slips, will be
completed by December 2007 at a cost of 70 million baht.
Phase 1 involves dredging a boat basin and the installation
of navigation markers, freshwater tanks, plumbing, electricity,
a fueling and water station, and a maintenance building.
With a budget of 300 million baht.
Second Phase was to include the construction
of a building on the pier to house administration, immigration
and customs services, an additional 166 yacht slips
and two breakwaters that were to be made with large
boulders.
|