The First Phase
of construction of the marina, which
involves building 44 of the originally-planned
210 yacht slips, will be completed by December
2007 at a cost of 70 million baht. Phase 1 involves
dredging a boat basin and the installation of
navigation markers, freshwater tanks, plumbing,
electricity, a fueling and water station, and
a maintenance building. With a budget of 300 million
baht.
Second Phase was to include the construction
of a building on the pier to house administration,
immigration and customs services, an additional
166 yacht slips and two breakwaters that were
to be made with large boulders.
|